Chiller plant with 1300 TR capacity, primary constant and secondary variable pumping system, and thermal energy storage.
The mall houses retail stores, cinemas, banquet halls, a gaming zone, and a food court, requiring a robust air-conditioning system. However, the facility faced operational challenges including:
During the chiller plant audit, Aerosys identified multiple design and operational inefficiencies:
These inefficiencies led to excessive energy consumption and O&M costs, with the plant running well below its design efficiency.
- Descaling the evaporator and condenser
- Replacing cooling tower fills
- Removed thermal storage tanks, PHE, and associated pumps
- Replaced 3-way AHU valves with 2-way valves
- Performed AHU water balancing
-Increased condenser inlet pipe size from 4” to 6”
-Balanced chilled water and condenser water systems
- Used existing field sensors and control systems for part load efficiency improvement
- Resolved low ΔT syndrome
By eliminating design flaws and improving plant efficiency, Aerosys delivered: